Project and community update

Works are progressing well at Lelley Fields Crematorium and we are now past the half way point of the project. As most will have seen, the steel frame and roofing works were completed back in May. The external blockwork has recently been completed, with the scaffolding removed revealing the size and shape of the building.

Internally the M&E install is well underway, the finishes have commenced with the plaster works currently ongoing and the joinery install is due to commence shortly.

Externally the hard landscaping is taking shape, half of the carpark and access road has received its tarmac base with the second half of the tarmac due in September. The paving works are progressing with the feature mound and sculpture now complete.

Looking a little in the future the cremator equipment will be delivered and lifted into location in early September. We are particularly looking forward to the turfing, seeding and planting commencing in October.

The project remains on programme for a completion date just after the new year in January 2023.