From Winter 2021, contractors, Kier Construction started on site.

Works carried out to- date:

  • Water attenuation is being installed to manage drainage on site and ensure slow release of water into ditches (at same speed as run off from agricultural land)
  • Temporary office space and car parking on site
  • Security fencing / hoardings installed with regard to visibility at the junction
  • Ditches have been cleared, land drainage around the site to get water into ditches
  • Ground works for car parking area and building foundations completed
  • Steel frame, roof and walls are in progress
  • Construction traffic management plan in place to minimise traffic through Preston